Arthur R. Bowman Dam Hydroelectric Project, FERC No. 11925


Arthur R. Bowman Dam (BOR photo)

Arthur R. Bowman Dam (formerly Prineville Dam) was built in 1961 as part of the U.S. Bureau of Reclamation's (BOR) Crooked River Project which was authorized for irrigation storage, flood control, recreation, and fish and wildlife management. The dam is an earthfill structure on the Crooked River about 20 miles upstream from Prineville Oregon.

The project, as proposed by Symbiotics LLC, will have an installed generating capacity of 6.8 MW. The project will utilize the normal regulated flow releases ranging from 140 to 550 cfs. Gross operating hydraulic head for the two 3.4 megawatt turbine/generator units will range between 110 to 150 feet. No modifications will be made to present structures upstream of the existing project outlet regulating gates. All proposed structure modifications and additions will be limited to the outlet conduit downstream of the regulating gates.


Estimated Monthly Power Production

As a run-of-river operation, the project will use only the available water released from the reservoir by the BOR. The estimated monthly power generation will range from 0.35 gWh in November to 2.83 gWh in April. On average, the annual production would be 18.5 gWhr.

The preliminary permit was issued by the FERC on August 7, 2001 to Symbiotics LLC. Two years later (August 11, 2003) Symbiotics submitted a Stage I Consultation Document to the agencies. Proposed studies were undertaken during the following year and are still continuing. On May 12, 2004, the Draft License Application (Stage II) was mailed and the Final License Application (Stage III) was submitted to the FERC July 30, 2004.

On August 13, 2004, the FERC made notice that the Bowman Application was accepted for filing and requested that agencies submit additional study requests. An acceptance or defiency letter is expected by the end of October 2004.

The following section contains links to available public documents for the project, as well as the proposed project boundary overlaid on a 1:24K USGS quad, and slideshows presented to the public by Symbiotics LLC. All documents are available in PDF format (please visit the Adobe Acrobat website for a free reader). The files tend to be large, and file sizes have been noted next to links as a warning. They may be more easily downloaded if you right-click on the hyperlink and choose "Save Target As..."

Project Documents

Cover Page, Table of Contents and Initial Statement (732 KB)
Exhibit A: Project Description (22 KB)
Exhibit B: Project Operations (36 KB)
Exhibit C: Construction History and Schedule (21 KB)
Exhibit D: Statement of Costs and Financing (15 KB)
Exhibit E: Environmental Studies Report (12208 KB)
Exhibit F: General Drawings (810 KB)
Exhibit G: Project Maps (1045 KB)

Download Entire Application (14816 KB)

Project Slideshows

Other Project Files

If you have comments regarding this project and wish to have them included in the consultation process, please address them to:

Brent Smith (bsmith@nwpwrservices.com)
Northwest Power Services
P.O. Box 535
Rigby, Idaho 83442
208-745-0834 (phone)
208-745-7909 (fax)